New Property Update – June 8, 2014

Things are moving full steam ahead at the new property to make way for the coming recreational fields and community center!

Here’s a quick look at some of the highlights. At this point, we are…

  • 100% complete with site clearing
  • 90% complete with the roadway rough-in (now utility crews can begin installation of underground electric, water, sewer, and gas)
  • 95% complete with leveling the recreation fields (should be completed in the next three weeks)
  • 40% complete on the storm water ponds

We’ve also begun architectural work on the main pavilion as well as a concept plan for the full campus. Floor plan drawings for the first community center building should be completed this summer.

Take a look at the following shots taken lately at the new property.

2 3 4